Hydro-Québec

Partager

To meet the growing demand for electricity and improve service quality in Montreal’s West Island, Hydro-Québec has launched a major project to contribute to increase capacity at Saint-Jean substation in Dollard-des-Ormeaux. 

Work to convert Saint-Jean substation to 315/25 kV began in 2021. The substation currently serves some 5,900 households and businesses in Dollard-des-Ormeaux, Pointe-Claire, Kirkland and Beaconsfield. With local energy needs on the rise, Hydro-Québec must upgrade the power system to improve service quality.

Planned work

The work will unfold in multiple stages over the next four years, and will include:

  • Dismantling of the remaining 12-kV equipment
  • Addition of electrical equipment, 25-kV capacitor banks and a third 315/25-kV transformer
  • Expansion of the control building to house the new 25-kV equipment
  • Connection of multiple underground lines to supply Montréal’s West Island more efficiently


Most of the work will take place on land owned by Hydro-Québec. However, two nearby municipal lots will also be used during the project, primarily for materials storage and secure site access. One of these sits at the intersection of De Salaberry and Saint-Jean; the other lies to the east of that intersection within the transmission line right-of-way along De Salaberry.

Hydro-Québec will implement a mobility management plan to limit the impact of the work and jobsite facilities on automobile, pedestrian and bicycle traffic. The company will also introduce measures to appropriately manage noise, dust and lighting.

The two municipal lots are expected to be in service from April 1, 2026, to December 31, 2029.

Work to be completed in 2030

The work is expected to continue until 2030. Once complete, the project will improve grid robustness and ensure a more reliable power supply to the area’s homes and businesses.

Dialogue with the community

Hydro-Québec is working closely with the city of Dollard-des-Ormeaux and held a webinar on March 26, 2026, to provide information and answer questions from the public about the work. 

Snake inventory

The snake inventory will take place from August 24 to the end of October 2026, depending on weather conditions.
Here are the main steps:

  • Installation of 12 artificial shelters and active excavations;
  • Weekly visits spread over a period of 6 to 9 weeks, for a total of 6 to 9 visits.

For more information, visit: Hydro-Québec | Snake Inventory

To learn more

A real commitment to a sustainable future!